Highway Department accepts low bid on Broadway Bridge replacement | Arkansas Blog

Friday, September 19, 2014

Highway Department accepts low bid on Broadway Bridge replacement

Posted By on Fri, Sep 19, 2014 at 4:05 PM

click to enlarge SOON TO BE A MEMORY: Before long, postcards such as this will be necessary to remember the Broadway Bridge, opened in 1923. It is to be replaced in a $98 million project that is to begin soon.
  • SOON TO BE A MEMORY: Before long, postcards such as this will be necessary to remember the Broadway Bridge, opened in 1923. It is to be replaced in a $98 million project that is to begin soon.

The Arkansas Highway and Transportation Department has accepted the $98.4 million low bid by a Kansas City construction company to replace the Broadway Bridge between Little Rock and North some 18 months shorter than earlier estimates, though the full term of the contract will stretch more than two years.

No start date for the work has been set yet. Earlier, the work was expected to begin in 2015.

The department's release:


The Arkansas Highway Commission and Arkansas State Highway and Transportation Department (AHTD) have accepted the $98.4 million bid from Massman Construction Company of Kansas City, Missouri, to replace the Broadway Bridge crossing the Arkansas River between downtown Little Rock and North Little Rock. This now becomes the single largest contract ever awarded by the Highway Commission.

The AHTD received four bids from across the country on the project:

* Edward Kraemer & Sons, Inc. $114.2 million

* Massman Construction Company $98.4 million

* PCL Civil Constructors, Inc. $114.4 million* 

* Brasfield & Gorrie,LLC $115.4 million

“We’re very pleased with the bids we received, particularly the bid from Massman,” stated AHTD Director Scott Bennett. “We gave contractors 12 weeks instead of four to develop  their bids hoping they would find innovative ways to keep both the cost and time down. We’re excited to begin this journey with Massman.”

Not only was Massman’s bid the lowest in terms of cost, their bid also was the shortest in terms of time for the bridge to be out of service. Original estimates were that the bridge could be out of service for up to two years.

“From the beginning, the length of time for the construction has been a major point of concern,” Bennett added. “While the bridge is out, 24,000 vehicles per day must find another way to cross the river. A six-month closure will certainly be less burdensome than two years."

The current project first gained attention in 2008 when the AHTD put it in its draft four-year construction program covering the years 2010-2013. Original cost estimates from the AHTD for a standard plate girder bridge were $58 million.

Pulaski County eventually agreed to contribute $20 million to the project for a more elaborate design, the double basket handle network tied arch, bringing the estimated cost to about $80 million in 2012.

The complexity of the design, unique steel fabrication requirements, and recently rising concrete and steel costs, combined with the need for a short construction timeline, had the AHTD concerned about the bids they were going to receive.

“Our latest estimates from this year had the project going for anywhere from $80 to $100 million,” Bennett stated. “Needless to say, the combination of a sub-$100 million bid and six-month bridge out-of-service window was good to hear.”

Still yet to be determined is when the current bridge will be taken out of service.

According to Bennett, “In the near future, we’ll begin working out the details with the contractor to determine the detailed sequence of construction. Once we have a firm timeline for when the current bridge will be closed, we will provide as much notice and information as we can.”

Bids were also accepted on Wednesday for a project to widen Interstate 40 to six lanes extending from Morgan eastward to the Interstate 40/Interstate 430 interchange.

McGeorge Contracting Co., of Pine Bluff was awarded a $38.36 million contract to complete the five-mile widening project, which includes modifications to the 40/430 interchange.

This is the last construction project needed to complete the widening of Interstate 40 to six lanes between North Little Rock and Conway. Completion is expected in mid-2016.

From the ArkTimes store

Favorite

Comments (9)

Showing 1-9 of 9

Add a comment

 
Subscribe to this thread:
Showing 1-9 of 9

Add a comment

More by Max Brantley

Readers also liked…

  • Auditor Lea caught not telling the truth

    State Auditor Andrea Lea, who began her tenure in statewide office with a degree of competence unseen in some other Republican counterparts (think Treasurer Dennis Milligan particularly), is becoming more deeply mired in a political scandal.
    • Mar 4, 2016
  • Free Zinn book for Arkansas teachers

    Arkansas teachers! Get your free Howard Zinn book here! Whether Kim Hendren likes it or not.
    • Mar 3, 2017
  • Another Republican miracle-working governor

    Great piece in Washington Post on the budget crisis in Louisiana. Big tax cuts and corporate welfare will do that to a state, particularly to a state whose previous governor, Republican Bobby Jindal, refused to join the Obamacare-funded Medicaid expansion. There's a lesson there for Arkansas.
    • Mar 4, 2016

Most Shared

Most Viewed

Most Recent Comments

Blogroll

 

© 2017 Arkansas Times | 201 East Markham, Suite 200, Little Rock, AR 72201
Powered by Foundation