Broadway Bridge contractor got a two-day headstart on six-month project

Posted By on Mon, Oct 17, 2016 at 7:14 AM

SAYING GOODBYE: Highway commissioners arrived in convertibles for the Sept. 28 closing of the Broadway Bridge. The contractor replacing the span had two days without traffic to begin work on removal of the bridge before start of a six-month period to finish the work.
  • SAYING GOODBYE: Highway commissioners arrived in convertibles for the Sept. 28 closing of the Broadway Bridge. The contractor replacing the span had two days without traffic to begin work on removal of the bridge before start of a six-month period to finish the work.

A reader posed a question about the Broadway Bridge project and the Times has an answer:

The question:

Any idea why the 180-day contract period on the new Broadway Bridge started October 1 at 12:00 a.m. since the bridge was closed on Wednesday September 28 in the late morning? Was Massman [the contractor] allowed to do any work between late that Wednesday morning until midnight Friday night, a little more than 2 1/2 days?

Quote below taken from: http://www.arkansashighways.com/

"This clock is the official countdown of that 180-day period, which began at 12:00 a.m. on Saturday, October 1st."

Looks like AHTD counts time the same way they do I-30 lanes, with funny math.
I asked Danny Straessle, spokesman for the Arkansas Highway Department, why the "clock" started Oct. 1 when the bridge closed Sept. 28.

We didn't start charging time against the 180-days until Oct 1st.

In an effort to help speed things along, it was closed 2.5 days before so we could get in the decommissioning ceremony and so the contractor could mill the asphalt off the bridge unimpeded by live traffic.

I followed up, asking why that didn't qualify as work on the bridge.

The alternative would have been two grueling last days of the bridge and for the motoring public with lane closures so they could mill the asphalt.

Additionally, we weren't really sure what removal of the asphalt would reveal (condition of original pavement underneath) and felt more comfortable keeping live traffic off it.

The contractor notified us they would be ready to close the bridge on October 1st. The ensuing discussion included fitting in the ceremony (without getting in the contractor's way) as well as the above mentioned pavement concerns.

In short, instead of the lane closures, we opted to just go ahead and close the bridge. Since Massman is working around the clock we wanted to pick a closing date/time so the public could participate in the ceremony and give anyone interested a chance to say goodbye.
They were doing more than milling asphalt before Oct. 1, as Brian Chilson photos taken Sept. 30 illustrate. One example:

_nkw2760_2000.jpg

Tags: , ,

From the ArkTimes store

Favorite

Comments (13)

Showing 1-13 of 13

Add a comment

 
Subscribe to this thread:
Showing 1-13 of 13

Add a comment

More by Max Brantley

Readers also liked…

  • Judge Griffen: Why black lives matter

    Another few words from Judge Wendell Griffen growing from the controversy over the sale of Black Lives Matter T-shirts at the state black history museum — removed by the administration and restored after protests from Griffen and others stirred by a story in the Arkansas Times:
    • Mar 13, 2016
  • Free Zinn book for Arkansas teachers

    Arkansas teachers! Get your free Howard Zinn book here! Whether Kim Hendren likes it or not.
    • Mar 3, 2017
  • Saturday's open line

    Got any thoughts? Put them here.
    • May 21, 2016

Most Shared

Most Viewed

  • Environmental group finds agricultural chemicals in Arkansas drinking water

    The Environmental Working Group released a report this week that asserts that the drinking water for about 200,000 Arkansans contains unsafe levels of chemicals related to industrial agriculture. Another environmental group has used the occasion to call for Tyson Foods to do something about it.
  • Ole Miss apologizes to Houston Nutt, settles his lawsuit

    Tom Mars, attorney for Houston Nutt, the former Arkansas and Ole Miss football coach, called my attention this morning to news that Nutt had settled his lawsuit against Ole Miss officials for speaking negatively about him despite a no-disparagement agreement with the school following his departure as head coach.

Most Recent Comments

Blogroll

 

© 2017 Arkansas Times | 201 East Markham, Suite 200, Little Rock, AR 72201
Powered by Foundation